Last work day for 2013, well for myself any how. Keith will be possibly down once more before year end but that depends on weather. On this last day, a couple of things occurrd. The day started by removing the west ladder, so that it can be cleaned during the next cold spell. It came off relatively easy and us now resting upon the adjecent conflat.
Work on the east side continues, with more paint being removed and matching the rest of the barrel currently sitting in a Barry condition. This will be easily removed and then primed when weather improves.
A completion date of June is seeming reasonable, with mainly painting the only work to be done.
The start of 2014 may also see the start of two other projects, more info can be found on our website
And finally, we wish all of our followers a Happy Christmas and a Happy New Year
GCR WAGON GROUP
Wednesday, 18 December 2013
Sunday, 24 November 2013
A surprising find
Just a quick post today. Work on Tuesday concentrated upon the east side of the barrel once more, with progress advancing even in this cold weather. Whilst cleaning back, the above was found. Believed to be apart of the original livery, it seems it is the contents logo, and was painted over in future re-paints. This will sit on the side until measurements have been taken, hopefully this Tuesday, then this can be cleaned and hopefully primed before Christmas.
With Christmas approaching, work is inevitably going to be hit and miss due to weather and commitments. Hopefully, the east side should be fully in primer before the new year.
Sunday, 3 November 2013
Update
Just a short post to update you all on latest progress.
Work has been continuing on the east side of the barrel. Approx 2/3rds of this side is now sitting in primer with the rest moving rapidly along. The group now has access to two ladders which makes it easier to attack both ends simultaneously. Hopefully the weather picks up before it gets worse so that it can have undercoated applied.
The brakes are still awaiting the support blocks which sit inside the metal bars for extra strength. These have been cut and are awaiting delivery. Apart from a couple of bolts missing from a couple of buffers, we would have thought the bottom may be done, however on Tuesday it was noticed the first layer of gloss seems to have a habit of flaking off. This generally seems to be the areas that have been previously cleaned before we started work, however it isn't a big job and will be corrected when we apply the second coat of gloss.
As you can read, a finish is definitely in sight, with the autumn gala 14 looking promising for its debut. If you would like to help in achieving this then do get in touch. Work isn't going to stop either once in service, we are already in discussion with our new project owner, as well as the intention to have multiple projects on going at once...keep your eyes posted on future posts
Work has been continuing on the east side of the barrel. Approx 2/3rds of this side is now sitting in primer with the rest moving rapidly along. The group now has access to two ladders which makes it easier to attack both ends simultaneously. Hopefully the weather picks up before it gets worse so that it can have undercoated applied.
The brakes are still awaiting the support blocks which sit inside the metal bars for extra strength. These have been cut and are awaiting delivery. Apart from a couple of bolts missing from a couple of buffers, we would have thought the bottom may be done, however on Tuesday it was noticed the first layer of gloss seems to have a habit of flaking off. This generally seems to be the areas that have been previously cleaned before we started work, however it isn't a big job and will be corrected when we apply the second coat of gloss.
As you can read, a finish is definitely in sight, with the autumn gala 14 looking promising for its debut. If you would like to help in achieving this then do get in touch. Work isn't going to stop either once in service, we are already in discussion with our new project owner, as well as the intention to have multiple projects on going at once...keep your eyes posted on future posts
Sunday, 29 September 2013
Brake, brake and erm ladder?
Just a quick blog today, mainly as the photos will speak more then I can.
The new look west side, with freshly painted axle boxes, axles, and brake gear all attached.
Another view showing the south and west sides. Not long now till a second coat will be applied followed by the all important branding.
Also re-attached is the east side ladder. This was cleaned and painted the back end of 2011 and was sitting on the adjecent conflat since. An imminent shunt in the yard has resulted in this being attached, however this also helps us as we can now start to attack the east side whilst we wait for A6071 to be moved to a suitable location where the scaffold can be left up.
Friday, 13 September 2013
Big update
You would be forgiven if you thought work had stalled. In fact its the complete opposite. Work has made great steps in the last couple of weeks, even with the change in weather.
Firstly, Keith has made good progress on the walkways on the top, as you may remember one had work started on it. These have both been fully cleaned, primed and undercoated. Whilst working on the walkways, he has also made progress on cleaning the main release valve, which again is now sitting in undercoat.
Two weeks ago we undertook a parts exercise, seeing which parts we had, and if any bolts/nuts were to be ordered. This resulted in a order of 10 a2 M16 bolts with nuts and 20 a2 m12 bolts with nuts as well as some spare wickworths nuts for existing bolts. Whilst doing this exercise, we discovered there was actually parts sitting in store that can actually be refitted.
Below are two photos showing newly attached items. These being 2 brake hangers as well as steam pipe work.
Firstly, Keith has made good progress on the walkways on the top, as you may remember one had work started on it. These have both been fully cleaned, primed and undercoated. Whilst working on the walkways, he has also made progress on cleaning the main release valve, which again is now sitting in undercoat.
Two weeks ago we undertook a parts exercise, seeing which parts we had, and if any bolts/nuts were to be ordered. This resulted in a order of 10 a2 M16 bolts with nuts and 20 a2 m12 bolts with nuts as well as some spare wickworths nuts for existing bolts. Whilst doing this exercise, we discovered there was actually parts sitting in store that can actually be refitted.
Below are two photos showing newly attached items. These being 2 brake hangers as well as steam pipe work.
A view of the steam pipe work, now re-attached to the pipes.
The first brake hanger back in place, a fiddly job if put on incorrectly as we found out, but that is how we learn.
This week saw a major advancement, and one that has taken a year to complete. The wheels, axles, axle boxes are now sitting in their final colour, nice lovely gloss black. These have been painted, between rain showers, and really give A6071 a view of the end. The west side brake rigging still needs to be re-attached as does the axle tie bar however once these are done, we can say A6071 can actually run.
A view of the completed axles, axles boxes and wheels on the west side.
A view of A6071 looking from the south.
A6071 is now sitting in its first coat on three sides. The East side still needs starting however this is being held up by an imminent shunt taking place within the yard. Hopefully A6071 shouldn't end up right down the yard as we have put a request for it to be moved by one wagon length.
Our next job is to finish the walkways on top, re-attach the release valve gear/wheel and then comes a job that im sure would seem easy at a glance, however is going to prove to be an all day job. This being the re-attachment on the east side ladder, then to take down the west side ladder. Apparantly a crowbar/hammer, wheatabix and a pot of tea may be needed. Look out for updates on this.
I'll close with my normal request for help. If we have inspired you to help then do get in touch. We have a list of wagons that we would like to start on as well as ones currently in the freight train needing a bit of TLC and we do have one of the biggest collections in the country for BR era wagons. They do not look after themselves and we are a small group, so help would be appreciated
Tuesday, 20 August 2013
Quick Update
Just a quick one this week.
Keith has finished cleaning out the inside of the tank, so much so there is an echo even when he is leaning out the tank. A photo will be attached next week showing how clean it now looks. He will be going in with a brush to just tidy up, then it will be inspected by Phil.
Work has continued on the steam valve. This has been cleaned and glossed, with the help of a spray can. Keith has been very busy as not only did he do the work inside the tank, he cleaned down the bolts for the steam valve.
Work for next week will focus on the main release pipe, and also a fitting exercise to see what bolts need to be ordered. If there is time, we may even start cleaning the east face.
Keith has finished cleaning out the inside of the tank, so much so there is an echo even when he is leaning out the tank. A photo will be attached next week showing how clean it now looks. He will be going in with a brush to just tidy up, then it will be inspected by Phil.
Work has continued on the steam valve. This has been cleaned and glossed, with the help of a spray can. Keith has been very busy as not only did he do the work inside the tank, he cleaned down the bolts for the steam valve.
Work for next week will focus on the main release pipe, and also a fitting exercise to see what bolts need to be ordered. If there is time, we may even start cleaning the east face.
Tuesday, 13 August 2013
A finish in site?
Last Wednesday work concentrated upon the axles. These have been cleaned, primed and undercoated. Whilst these were being cleaned, date stamps were found. The south Axle dates from 1927 where as the north axle is 1948. The south west wheel has now been undercoated as well. These are all going to be glossed on the same day, along with the north west wheel. Below is a photo of the newly undercoated south axle.
Keith was busy on Saturday. All the west brake components have now been fully glossed and are now ready to be re-attached. These will be re-attached once he has finished cleaning the inside of the barrel. Whilst Keith had the gloss out, he also applied the first coat to the south end face of the barrel, now meaning THREE yes THREE sides are now in black gloss. The picture below was taken this morning before work commenced.
To today's report. Keith once again has been inside the barrel scraping the rust and dirt from inside. Its a big job and a real difference can be seen when looking in. He believes one more day inside and it should be clean, depending on results from inspection by Phil. The long term aim is to use A6071 as a water carrier for the engines, so the insides do have to be suitable.
For me, work concentrated on taking the steam valve off the side of the tank. A few months back, Keith applied grease to release the nuts, making them easy to take off. The only reason it wasn't taken off then was it was tightly fitted. For a job that would take approximately 5 mintues from looking at it, it instead took an hour to free. Cleaning it up is going to be a big job. The main issue is that it is made out of brass like material, meaning using an angle grinder with wire brush is not a suitable method. Next week I will try cleaning it up with some Brasso. Below is a photo showing where the steam valve is attached.
The main work is now focused on several areas again. The list of items to be done is growing, not shrinking and the list in summary is below.
- Clean and paint the west walkway
- Clean and paint the valve pipe (runs through the tank, only top half to be done)
- Gloss the west coast wheels, axles and axle boxes
- Clean and paint east side of barrel
- Clean up steam valve
- Attach wood blocks to brakes.
- Re-attach west side brakes
- Clean and paint the west ladder
- re-attach the east ladder
- second coat the barrel in gloss
- apply logos
- apply small writing
- attach new wagon plates
- re-assemble discharge pipes